HUESKER Ltd.
Space2work Warrington
Winwick Quay
WA2 8LT Warrington
United Kingdom
Workers are laying Fortrac on a building site

Geogrids enable bridge ramp construction

Project information

Construction project

Upgrading of State Road 2183

Customer

Staatliches Bauamt Bayreuth

Construction

Scharnagl Hoch- und Tiefbauunternehmen; Centrum Pfähle

Location

Bindlach , DE

Planing

EDR-Ingenieurbüro

Construction time

August to October 2012

Products used

Project details

Foundation of the dams on precast concrete driven piles with a geogrid-reinforced foundation pad
Rollers work the ballast over the Fortrac

Situation

The extension of State Road 2183 north of Bindlach requires the construction of a bridge structure to eliminate a level crossing. During the first construction phase, the bridge structure had already been founded on in-situ concrete piles. In the subsequent construction phase, the task was to connect the bridge approach to the existing structure without settlement. To this end, the Technical University (TU) of Munich was commissioned to determine a suitable foundation method, taking into account the structure’s location within a water protection area.

 

Solution

The Technical University of Munich examined 20 different foundation methods and ultimately recommended founding the embankments on precast concrete driven piles with a geogrid-reinforced foundation pad. With this foundation method, the loads from the bridge approaches are transferred via the geogrid-reinforced foundation pad into the piles, which transfer the forces to the deeper, load-bearing red sandstone. This enables a settlement-free connection to the bridge structure, and any joints are reduced to a minimum. For the foundation method described, a pile-ready subgrade is first constructed. The approximately 1,700 precast concrete driven piles are then installed. These are cut to a uniform height, and the piles and pile cap plates are connected using concrete. The spaces between the pile caps are then filled with fill material, so that the geogrids, which distribute the forces evenly into the piles, can be laid on the subgrade. After the fill material has been placed, the geogrids are anchored by folding them back and the fill material is compacted.

 

Advantages

  • Virtually no settlement during construction or operation.
  • No waiting times for consolidation, as the soft ground is practically unloaded.
  • Relatively short construction time.
  • The structure can be put into service immediately.
  • Reduced transport of materials.
  • Suitable for use in water protection areas
  • Pre-cut roll lengths

Further information

you can find here
Brochure IconBrochure Icon
Product-related brochures