Erosion Control on a New Scale – Cottbuser Ostsee
Project information
Construction project
Cottbuser Ostsee – Erosion Protection of the Flooding StructureCustomer
LEAGConstruction
Richard Schulz TiefbauLocation
Cottbus, Brandenburg , DEPlaning
Sweco / HUESKERConstruction time
2017/2018Products used
Project details


Situation
For more than 30 years, around 220 million tonnes of lignite were extracted from the Cottbus-Nord open-cast mine. Following the end of mining operations in December 2015, work began to transform the residual mining pit into Cottbuser Ostsee. The lake has been fully flooded since December 2024. With a surface area of 18.8 km², it is Germany’s largest artificial lake. A flooding structure was constructed on the western slope to fill the lake, conveying water from the Hammergraben, a tributary of the River Spree, into the lake. In total, approximately 280 million m³ of water passed through the structure. Around 126 million m³ of this volume filled Cottbuser Ostsee. The remaining water served to replenish the surrounding geological formations, where groundwater levels had been lowered for decades to enable open-cast mining. The main challenge was to protect the existing sandy soil against erosion. On its way to the bot tom of the developing lake, the water had to pass through the approximately 160 m long flooding structure, overcoming a height difference of around 40 m and slopes of up to 28°. With a maximum discharge of 5 m³/s, the structure required continuous erosion protection capable of withstanding high hydraulic loads.
Solution
The Incomat 20.115 A8S geotextile concrete mattress was used for erosion protection. Once filled with concrete, it forms a continuous revetment with an average thickness of 17 cm. The prefabrica ted mattresses were installed on the profiled channel and filled with in-situ concrete. The flexible textile formwork follows the geometry of the underlying surface.
The flooding structure consists of a permanent and a temporary section. The approximately 40 m long permanent inlet structure receives water from the Hammergraben via a DN 1600 pipe. The pipe outlet is integrated into a gabion wall that also forms the upstream end of the structure. The trapezoidal channel has an 8 m wide base with a dry-weather channel. Incomat protects the channel base and parts of the slopes against erosion. Directly ad joining this section is the approximately 120 m long temporary inlet structure, which conveyed the water down the slope to the future lake bed. Today, this section lies completely below the wa ter surface. For installation in sections, the Incomat erosion protection sys tem was divided into individual panels. The upper panels over lap those below by at least two metres, protecting the transitions against undermining. The panels were installed against the di rection of flow, connected to each other, secured on the slope and subsequently filled with concrete. With a total length of around 160 m, this created the largest inlet structure constructed with Incomat up to that time
Advantages
The Incomat geotextile concrete mattress system combines high hydraulic resistance with a high degree of flexibility. This made it possible to create a continuous concrete revetment across the steep and complex channel geometry, reliably protecting the existing sandy soil against erosion. The flexible mattress follows the profiled surface, while the overlapping panels protect the transitions against undermining. In this way, the system meets the high hydraulic demands of the flooding structure while adap ting to its challenging geometry.